We use cookies to ensure you get the best experience while visiting our website.
By clicking 'Accept' you consent to our use of cookies. For more information on how we use cookies please see our cookie policy.

Text size A A A

Coupar Angus

Scotland’s first biomethane plant at Coupar Angus was commissioned in December 2014

About:

The Keithick Biogas plant at Coupar Angus, Perth, Scotland was commissioned in December 2014. The plant processes 1200 cubic metres an hour of biogas using water-wash scrubbing technology. Up to 560m³ of biomethane is injected to the grid hourly into Scotland Gas Networks medium pressure network.

 

Our role:

Investment

Our investment in the project includes installation of biomethane assets on site, grid entry unit and export pipeline.

 

Development

We played a key role in developing the project which comprised undertaking grid capacity planning and design, managing network contracts, producing a fully integrated design, that included safety systems, gas quality risk assessments, civil, mechanical, electrical and instrumentation.

 

Construction

We installed all infrastructure from the AD interface through to the connection to the gas network. Our installation included biogas upgrader, propane tanks, pressure regulators, gas-entry-unit (GEU), 500m pipeline and connection. Our team oversaw the project management through to commissioning and beyond.

 

Post commissioning

Our engineers were on hand to provide support and expertise through the early stages until the plant was fully operational.

 

Maintenance and support

We continue to provide a full maintenance package, including routine visits, planned and reactive maintenance and refining plant operation to maximise output. We also provide a liaison role with the network operator SGN.

 

Green Impact:

More than 18 million cubic metres of biomethane injected to the grid since commissioning. The Keithick Biogas plant produces green gas to supply over Scottish 4,200 homes. This is a carbon equivalent saving of 9,300 tonnes per annum.

 

Performance improvements:

By working closely with our partners, we have helped to optimise the plant and increase productivity of biomethane from 2.4 million m³ in year one to 4.1 million m³ injected into the grid in 2019.